"Chris Burke is incredibly smart and is a strategic thinker."
- Chambers and Partners, Chambers USA Guide 2023
Chris Burke has over 20 years of experience litigating construction disputes both domestically and internationally. Chris has tried multiple disputes through final award, with amounts in dispute of over US$1 billion.
Chris represents clients in state and federal courts and in arbitration proceedings, and has considerable experience with international dispute resolution. Chris represents owners, general contractors, construction managers, and subcontractors through the various stages of dispute resolution, from claim preservation through trial.
Before maturation of the litigation process, Chris works with his clients to avoid costly disputes by resolving issues at the project level. Once litigation is inevitable, however, Chris handles all aspects of the dispute process. He is a seasoned litigator who protects his clients' economic interests while preparing for the best presentation at trial should a matter "go the distance." He also advises clients on non-contentious matters, including contract drafting.
Chris is a frequent author and speaker in the construction law space and is active in both the American Bar Association and International Bar Association.
Chris graduated cum laude from Yale University and later from the University of Virginia School of Law, where he served as a Dillard Fellow Legal Research and Writing Instructor.
Representative Experience
Currently representing a contractor in disputes with the project owner on an 800MW offshore wind farm off the United States East Coast.
Currently representing a pipeline contractor in a litigation with the project owner on a water pipeline project in Pennsylvania.
Currently representing an EPC contractor in a AAA arbitration with the project owner on a 70MW solar power plant in North Carolina.
Represented an ENRS. Top 40 contractor in a AAA / ICDR arbitration with an EPC contractor on a 674MW natural gas-fired combined-cycle plant in Massachusetts. Chris served as co-lead trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award of over US$25 million on its claims of, among other things, lost productivity and change order work. Chris’s client was also awarded its attorneys’ fees and costs.
Represented an EPC Contractor in an ICC arbitration with a subcontractor on a 600MW coal-fired plant in South America. Chris served as lead trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award upholding his client’s default termination, awarding in excess of US$11 million, and denying nearly all of the subcontractor’s US$30 million delay and disruption claims. Chris’s client was also awarded its attorneys’ fees and costs.
Represented a developer in an ICC arbitration with an EPC contractor on a 300MW coal-fired CFB power plant in Guatemala, and with a total amount in dispute of over US$1 billion. Chris served as trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award awarding damages of over US$300 million, and upholding his client’s default termination. Chris’s client was also awarded its attorneys’ fees and costs.
Represented a general contractor concerning the construction of a new 18-story courthouse in Las Vegas, NV. Chris served as trial counsel and following a 10-week arbitration hearing wherein, Chris’s client obtained a Final Award of $52.7 million on its affirmative claims and defeated nearly all of Owner Clark County's $60 million counterclaim.
Represented an ENR U.S. Top 30 general contractor in a dispute with a museum owner on a US$250 million modern art museum in Maryland. The parties reached a confidential settlement prior to the trial of the matter.
Represented a general contractor joint venture (comprised of three ENRS. Top 50 contractors) in an arbitration concerning the design and construction of a US$1.5 billion data center in Utah. The eight-party case proceeded through one week of an American Arbitration Association evidentiary hearing before reaching settlement after Chris’s joint venture client put on its affirmative case.Represented an ENRS. Top 10 contractor engaged in a dispute with its subcontractor over the engineering and construction of a 600MW petroleum coal-fired CFB power plant. Following the first five-week phase of a scheduled eight-week arbitration hearing, during which Chris served as trial counsel, Chris's client and the opposing party were able to achieve a confidential settlement of their disputes
Represented an EPC contractor in an ICC Arbitration dispute with its subcontractor over performance on a 300MW solar power plant in Arizona. The parties reached a confidential settlement prior to the evidentiary hearing of the matter.
Recent Publications and Presentations (Previous Five Years)
Disclaimer
Varela, Lee, Metz & Guarino updates the content of this website on a periodic basis. Any content i) is for informational purposes only and does not constitute legal advice; and, ii) is not intended to create, and your receipt and/or use of such content does not create, a lawyer-client relationship. You should not rely on any such content without first consulting a licensed attorney familiar with your particular facts and legal issues.